Updated for Awaab's Law Phase 2 commencing 30 November 2026 and the 2026 amendment regulations (SI 2026/1195).
How do housing associations comply with Awaab's Law?
By Katie Richardson, Operations Director · Reviewed and maintained by Jigsaw Conferences' Emergency Accommodation & Housing Team
This content is independently researched using official UK Government guidance and recognised housing sector sources. It is reviewed regularly by Jigsaw Conferences' operational housing team and reflects current best practice at the time of publication. It is provided for general information only and should not be considered legal advice.
Quick answer
Meeting Awaab's Law is largely an operational task. Housing associations that meet it consistently run four capabilities: a triage process that recognises hazards fast, competent investigation capacity, contractor capacity to make homes safe within five working days, and accommodation arranged in advance for the cases that cannot be fixed in time. From 30 November 2026 all four must cope with seven more hazard types. Jigsaw supports the accommodation element only; landlords should take their own legal advice on their obligations.
What does an Awaab’s Law compliance workflow look like?
The operational chain, end to end:
- Awareness — every channel (calls, emails, contractor reports, damp sensors) feeds one hazard log with a timestamp, because deadlines run from awareness, not from formal complaints.
- Triage — a documented decision: emergency (24-hour track) or potential significant hazard (10-working-day track), using what is known about the actual household. From 30 November 2026 the tests are what a reasonable landlord would make safe within 24 hours or 15 working days.
- Investigation — a competent investigator, findings recorded in a format that becomes the tenant’s written summary within 3 working days.
- Remediation — safety work within 5 working days of the investigation concluding; preventative work begun within 5 working days or at latest 12 weeks.
- Decant trigger — if relevant safety work will not be complete by the deadline, the alternative accommodation requirement applies from that point; suitability assessment and sourcing should start as soon as the forecast slips, not on deadline day.
- Evidence — every step timestamped: attempts to access, decisions, communications, placements, extensions and the return move.
What pressure is the sector actually under?
- Industry best practice
A 2026 sector survey reported that around 70% of landlords were meeting Awaab’s Law requirements more than 90% of the time — but flagged capacity strain and inconsistent interpretation, with a 14% rise in properties held empty for potential decants.
- Legal requirement
Phase 2 (30 November 2026) extends the same deadlines to significant hazards in seven further categories. The timescales stay fixed, so landlords should plan for more cases running on them.
- Industry best practice
Industry commentary from Procurement for Housing stresses that a 24-hour response depends on out-of-hours decision-making authority, tested contractor capacity and access to more than one accommodation option — not only an emergency phone line.
- Jigsaw delivery experience
Holding void properties for decants ties up rental income. External accommodation supply — hotels and serviced apartments on demand — converts that fixed cost into a variable one, paid only when a decant actually happens.
Void retention vs external supply — how do decant strategies compare?
| Criterion | Holding voids for decants | Pre-contracted external supply |
|---|---|---|
| Cost model | Fixed — lost rent whether used or not | Variable — cost only when a household is placed |
| Speed | Fast if a void matches the household; slow if not | Depends on availability at the time; wider reach across hotel and apartment inventory |
| Suitability match | Limited to your own stock profile | Matched per household — size, catchment, accessibility, pets |
| Audit trail | Internal records | Provider reporting: one invoice per case, coded to your references |
| Phase 2 scalability | Capped by void numbers | Scales with case volume |
Which KPIs prove compliance to your board and the regulator?
The measures we see mature landlords reporting monthly:
- % of emergency hazards investigated and made safe within 24 hours
- % of significant-hazard investigations completed within 10 working days
- % of written summaries issued within 3 working days
- % of safety works completed within 5 working days
- Decant activation time — hazard confirmed to household placed (target: same day)
- Placement suitability breakdown rate — moves that fail and need re-placement
- Cost per decant night, hotel vs apartment, benchmarked quarterly
Downloads
Awaab's Law timescales — quick-reference PDF
One page. Every deadline, both hazard types, all three phases. Free — no email needed.
Free PDF — no email neededEmergency Accommodation Procurement Toolkit (Awaab’s Law edition)
Supplier question bank, evaluation criteria, KPI scorecard and audit-trail checklist for procurement teams.
Housing association questions answered
Do we need HHSRS-qualified staff to investigate?
The regulations require a competent investigator: a person who, in the landlord’s reasonable opinion, has the skills and experience to determine whether the home is affected by a significant or emergency hazard. Document the competence decision — it is part of the evidence trail.
How should we prepare for Phase 2 on 30 November 2026?
Review your repairs data for the seven added hazard types, then stress-test investigation capacity, contractor capacity and accommodation supply against that volume. On accommodation, check who can authorise a placement out of hours and whether you have more than one option for large families and accessible needs. Our Phase 2 emergency accommodation readiness guide has a test you can run.
Can we use one provider for both planned and emergency decants?
Yes, and it simplifies governance — one supplier assurance exercise, one billing route, one audit trail. Jigsaw handles planned programme decants and emergency placements under the same account, with out-of-hours access for contracted clients. Guidance and industry commentary both point towards not depending on a single supply type.
What does the Housing Ombudsman look for when a case fails?
The timeline. When the landlord knew, what was decided, what was communicated to the resident and when, and whether alternative accommodation was offered once deadlines were at risk. A complete, timestamped file is the strongest defence — and the strongest driver of good outcomes.
Evidence · Real delivery
How do you house 60 NHS key workers across three cities at once?
A rolling programme for an NHS trust — one monthly invoice, 98% occupancy satisfaction, around 40% below equivalent hotel rates.
Read the case studyFacing a live decant or planning accommodation contingency?
Our accommodation team supports landlords and insurers with emergency and decant placements — hotels for the first nights, serviced apartments for longer repairs, one auditable invoice. Free to the client.
Related knowledge
Official legislation & guidance
Related articles & guides
Sources and authorities
Applies to England. Checked on 18 November 2026. The Regulations are the law; GOV.UK guidance is non-statutory; industry commentary is context only.
- Hazards in Social Housing (Prescribed Requirements) (England) Regulations 2025 (SI 2025/1042)
- Hazards in Social Housing (Prescribed Requirements) (England) (Amendment) Regulations 2026 (SI 2026/1195) — made 13 November 2026, in force 30 November 2026
- GOV.UK — Awaab's Law Phase 2: guidance for social landlords (non-statutory; applies from 30 November 2026)
- GOV.UK — Awaab's Law Phase 2: hazards guidance for social landlords
- Procurement for Housing — 24-hour emergency repairs under Awaab's Law (industry commentary, not legal authority)
Published 11 August 2026 · Last updated 18 November 2026 · Legislative statements verified 18 November 2026 against GOV.UK and legislation.gov.uk (sources cited inline).